Building a padel court · 2 July 2026 · 10 min read

How to plan the construction of a padel court so members experience as little disruption as possible

Building a padel court without disrupting members? Find out how to plan construction phases, timing and communication smartly. Includes checklist and practical step-by-step plan.

How to plan the construction of a padel court so members experience as little disruption as possible
In this article
  1. How long does it take to build a padel court on average?
  2. What phases are there in the construction process of a padel court?
  3. When is the best time to build a padel court?
  4. How do you, as a club, communicate the construction period to members?
  5. What are the biggest sources of disruption during the construction of a padel court?
  6. How do you make sure other courts remain accessible during construction?
  7. What do you need to arrange before construction starts to prevent delays?
  8. Frequently asked questions

Building a padel court requires more planning than most clubs expect. Not because the construction process is so complicated, but because the timing and communication around the work directly determine how much disruption members experience. A well-prepared build need hardly clash with the day-to-day use of the facility. Below you will find a practical overview of everything you need to know to make construction run smoothly.

How long does it take to build a padel court on average?

Installing a padel court takes an average of 3 to 4 days per court. The total process, including production, delivery and installation, takes an average of 10 to 12 weeks. If you also include the permit process, you quickly end up at 5 to 6 months for a complete outdoor project.

Those 10 to 12 weeks are made up of several phases: the production of the steel structure, transport, the foundation work and finally the installation itself. For an indoor court in an existing hall the process can be shorter, because the foundation is less complex. For an outdoor court the soil conditions play a major role and preparation can take more time.

Important to know: installation on site is relatively quick. Allow two days for the cage structure and one to two days for the artificial turf. Most of the time goes into preparation, not into the building itself. Anyone who understands that also plans better.

What phases are there in the construction process of a padel court?

The construction process of a padel court consists of five consecutive phases: preparation and permit, groundwork and foundation, installation of the steel structure, installation of glass and artificial turf, and finally the LED lighting and completion. Each phase has its own lead time and dependencies.

Phase 1: Preparation and permit

Before a single spade goes into the ground, the permit application must have been submitted. For outdoor courts an environmental permit is almost always mandatory. The average processing time at a municipality is 8 to 12 weeks. During this phase the structural calculations, the acoustic study and the site plan are also prepared.

Phase 2: Groundwork and foundation

The foundation is the most location-dependent phase. Depending on the soil conditions, the choice is drainage concrete (a water-permeable concrete floor that drains rainwater directly), Supersub (a lightweight foam concrete that can be poured in as little as one day) or ZOAB asphalt (a porous asphalt variant). This phase is also the most burdensome for the immediate surroundings: machines are on site, the ground is worked and there is construction traffic.

Phase 3: Steel structure and glass

After the foundation comes the installation of the cage structure. This goes quickly: two days for the steel structure, after which the glass walls are installed. This is the most visible phase for members and bystanders.

Phase 4: Artificial turf and finishing

Laying the artificial turf takes one to two days. After that comes the installation of the LED lighting and any additional components, such as sound-absorbing panels.

Phase 5: Completion and inspection

After completion, an inspection follows. For official matches, an inspection by Kiwa ISA Sport is mandatory. Kiwa ISA Sport is the recognised inspection body in the Netherlands for sports infrastructure. All foundation components must meet their standards. Anyone who works with certified materials avoids surprises at this inspection.

When is the best time to build a padel court?

The best time to build a padel court is from October through February. Outside the busy season, court occupancy is lower, there are fewer active members and the disruption for the club is minimal. In addition, contractors and construction crews are generally more available in this period.

For tennis clubs that are also active in winter, things are different. In that case spring, in April or May, offers the best balance: the summer season has not yet started, but the weather is stable enough for outdoor work. Note: for outdoor courts, a period of frost is a risk factor for foundation work. Always discuss this with the contractor.

Do you want the court ready for the new season? Then plan backwards. If you want to play in May, the permit application must have been submitted in November or December. That sounds early, but lead times are long enough to surprise you if you start too late.

How do you, as a club, communicate the construction period to members?

Good communication about the construction period starts early, is honest about the disruption and gives members a clear picture of the end date. Use several channels at the same time: a newsletter, a message on the club website, a post on social media and a notice in the changing rooms or clubhouse.

Make sure you share the following information:

  • The start date of the work and the expected end date.
  • Which courts or facilities will be temporarily unavailable.
  • Which alternative courts or times remain available.
  • Who members can contact with questions.

Also communicate along the way. A short message halfway through the build, with a photo of the progress, keeps members engaged instead of frustrated. People accept disruption better when they feel they are being kept in the loop.

Be realistic about the schedule. Give an end date you can deliver on, not the most optimistic version. A court that is ready two weeks later than promised feels like a failure. A court that is ready on time feels like a success, even if the construction itself was messy.

What are the biggest sources of disruption during the construction of a padel court?

The three biggest sources of disruption during the construction of a padel court are construction traffic and machinery during the groundwork, noise during the installation of the steel structure and limited access to adjacent courts or facilities. The foundation phase is generally the most burdensome period for the surroundings.

In concrete terms, you can allow for the following:

  • Groundwork: excavators, lorries with building materials and pouring concrete cause noise, vibrations and mud on the access roads.
  • Steel structure: installing the cage structure involves hammering noises and sometimes a crane that takes up space on the site.
  • Barriers: a safety zone around the building site is mandatory, which means adjacent courts may be temporarily inaccessible.
  • Dust and dirt: in dry weather, groundwork can cause dust that spreads across the site.

Installing the artificial turf and the LED lighting are relatively quiet phases. Anyone who schedules the most disruptive work outside peak hours limits the nuisance considerably.

How do you make sure other courts remain accessible during construction?

Other courts remain accessible by clearly fencing off the building site, separating routes for construction traffic from the routes for members, and phasing the work so that not everything is blocked at once. Discuss this with the contractor in advance and record it in the schedule.

A number of practical measures help:

  • Agree with the contractor at which times heavy equipment will be present and align this with moments when few members are at the club.
  • Provide a clear route for construction traffic that does not run past the existing courts or changing rooms.
  • Mark the safety zone around the building site with fences or tape, so members know where they may not go.
  • If several courts are built at the same time, phase the work per court so that part of the facility is always available.

For larger projects, such as building four or more courts, it pays to draw up a temporary playing schedule. That way everyone knows in advance which courts are available and members can adjust their training sessions without being caught off guard.

What do you need to arrange before construction starts to prevent delays?

To prevent delays, before construction starts you should have arranged at least the following: an irrevocable environmental permit, an approved structural calculation, a final construction order with a fixed start date and a site check for the foundation. Anyone who picks up one of these items too late risks weeks of delay.

A handy checklist for the preparation:

  1. Permit: submit the application in good time. Allow 8 to 12 weeks of processing time at the municipality. Without an irrevocable permit, construction may not start.
  2. Structural calculation: have the steel structure calculated based on the specific site, including wind load and any sound-absorbing panels. This is not standard work.
  3. Soil investigation: have a cone penetration test carried out to determine the soil conditions. This is the basis for the foundation advice.
  4. Utility connections: make sure electricity is available for the LED lighting. Arrange this well in advance with the grid operator.
  5. Material certification: check that all foundation components have been inspected by Kiwa ISA Sport. Non-certified materials are not permitted for competition use and can lead to rejection at the final inspection.
  6. Communication plan: draw up a communication plan for members before construction starts, not afterwards.

Anyone who has all these points in order before the start date avoids the most common causes of delay. For building a padel court, we at I-Padel guide the entire process, from permit application to completion. We are happy to advise you without obligation on the planning and the possibilities for your site.

Frequently asked questions

Can I build a padel court without an environmental permit?

In most cases an environmental permit is mandatory for an outdoor padel court, especially if it is a permanent structure. In exceptional situations, such as temporary or movable courts inside an existing building, a permit may not be needed, but this depends heavily on the location. Always check this in advance with your municipality to avoid fines or forced demolition.

What are the most common mistakes clubs make when planning a padel court?

The most common mistake is underestimating the lead time of the permit process. Clubs start the application too late and therefore miss the desired playing season. A second common mistake is skipping the soil investigation, so that the choice of foundation afterwards does not match the actual soil conditions and extra costs and delays still arise.

How do I know which type of foundation is best for my site?

The right choice of foundation, whether drainage concrete, Supersub or ZOAB asphalt, depends on the soil conditions, the drainage system on the site and the available budget. A cone penetration test (soil investigation) provides insight into the load-bearing capacity and composition of the soil. Have this investigation carried out before you accept foundation advice, so that the recommendation is based on factual data from your specific site.

What does building a padel court cost on average and which cost items should I expect?

The total investment for a padel court generally ranges between €40,000 and €80,000 per court, depending on the type of structure, the choice of foundation, LED lighting and any extras such as sound-absorbing panels. The biggest cost items are the steel structure and glass, the foundation and the LED lighting. Also allow for additional costs such as the soil investigation, permit fees and the Kiwa ISA Sport inspection.

How long does a padel court last and what maintenance is needed?

A well-built padel court has a lifespan of 15 to 25 years for the steel structure and the glass. The artificial turf has a shorter lifespan and is replaced on average after 8 to 12 years, depending on use and maintenance. Regular maintenance, such as brushing the artificial turf, checking the glass fixings and cleaning the drains, extends the lifespan considerably and prevents costly repairs.

Can I have several padel courts built at the same time, and does that bring advantages?

Yes, building several courts at the same time is advantageous both logistically and financially. The mobilisation costs for equipment and construction crew are shared across several courts, which lowers the average cost per court. In addition, the total construction period is shorter than if you have courts built separately. Do make sure you phase the work so that part of the facility is always available to members.

What do I need to arrange if the completed padel court does not meet the Kiwa ISA Sport standards?

If the court does not pass the inspection, the contractor is responsible for the repair, provided you have agreed that certified materials will be used and that the court must be suitable for competition. Record this contractually in advance. Preferably work with a contractor who has demonstrable experience with Kiwa ISA Sport inspections, so that the chance of rejection is minimal and any repair work is resolved quickly and at no extra cost.