Building a padel court · 10 June 2026 · 13 min read
How quickly can a padel court be operational?
Building a padel court takes 10–12 weeks on average. Find out about all the phases, what determines the lead time and how to avoid delays.

In this article
- How long does it take on average to build a padel court?
- Which phases are there in the construction process of a padel court?
- What determines how quickly a padel court is ready?
- How long does the foundation of a padel court take?
- Why does an outdoor court take longer than an indoor court?
- How quickly can a padel court be delivered if the structure is produced in-house?
- What are common mistakes that delay the handover of a padel court?
- Frequently asked questions
Building a padel court takes time, but how much exactly? Installing the cage structure and the artificial turf takes 3 to 4 days on average. The total lead time of a project, including production, delivery and installation, is 10 to 12 weeks on average. In addition, allow for any permit procedures, which take an extra 8 to 12 weeks on average.
Whether you want to expand a sports hall with several indoor courts or are a tennis club looking to build its first outdoor court: planning the construction of a padel court requires insight into the different phases. Below, we explain per step what you can expect and where most of the time goes.
How long does it take on average to build a padel court?
The construction time of a padel court is 3 to 4 days on average for installation on site. The total project lead time, from first quote to handover, is 10 to 12 weeks on average. This includes the production of the steel structure, transport, foundation work and installation of artificial turf and LED lighting.
Those 10 to 12 weeks are a realistic average for an indoor padel court without special complications. For outdoor courts, sites with complex foundation conditions or projects that require a permit, the lead time quickly increases. A permit procedure alone takes 8 to 12 weeks on average, and that period runs in parallel with the rest of the preparation if you plan smartly.
The installation itself goes relatively quickly: the cage structure is generally up in two days, and the artificial turf is laid in one to two days. Most of the time therefore does not go into the construction itself, but into the preparation: production, planning, foundation and logistics.
Which phases are there in the construction process of a padel court?
Building a padel court proceeds in five consecutive phases: preparation and design, foundation work, production and delivery of the steel structure, installation on site and handover. Each phase has its own lead time and depends on the previous one.
Phase 1: Preparation and design
In this phase the site is assessed, structural calculations are made and, if necessary, a permit application is submitted. This is also the moment when choices are made about the type of foundation, the specification and options such as LED lighting or sound-absorbing panels. Good preparation prevents delays later in the process.
Phase 2: Foundation work
Depending on the chosen foundation type (drainage concrete, Supersub or ZOAB asphalt) and the soil conditions, the foundation work takes one to several days. After pouring, the foundation must cure before the cage structure can be placed. This is one of the most time-determining phases, especially for outdoor courts.
Phase 3: Production and delivery
The steel structure is produced and made to measure for the site. Transport planning and logistics determine when the materials arrive on site. The shorter the chain between production and delivery, the less delay occurs here.
Phase 4: Installation
The cage structure is placed in two days. This is followed by laying the artificial turf in one to two days, including sand bed and lines. LED lighting is installed at the same time or immediately afterwards.
Phase 5: Handover
After installation, an inspection and handover follow. For official matches, an inspection by Kiwa ISA Sport is mandatory. This is a recognised body that checks whether the padel court meets the standards of NOC*NSF and the KNLTB. Schedule this inspection in good time, so that you do not have to wait unnecessarily to open.
What determines how quickly a padel court is ready?
The speed at which a padel court is operational is determined by four factors: the permit lead time, the complexity of the foundation, the availability of materials and the scheduling of the installation crew. Of these four, the permit is often the most decisive factor.
For an indoor padel court in an existing hall without structural modifications, a separate building permit is sometimes not needed. That immediately saves 8 to 12 weeks. As soon as you build outdoors, or when noise or lighting affects the surroundings, an environmental permit is almost always mandatory. Take that into account in your planning.
In addition, the soil conditions play a major role. On sites with poor bearing capacity or special groundwater conditions, the foundation work takes more time. A cone penetration test of the soil in advance gives insight into what is needed and avoids surprises during execution.
Finally: the availability of production capacity and the installation crew determines when it is your turn. Popular periods, such as spring and summer, are busier. Planning early pays off.
How long does the foundation of a padel court take?
Pouring the foundation generally takes one day, but the curing time afterwards determines when installation can begin. For drainage concrete and ZOAB asphalt this is usually two to seven days. Supersub, a foundation solution based on foam concrete, can in many cases be poured within a single day and can be worked on relatively quickly afterwards.
Drainage concrete is a water-permeable concrete floor in which rainwater drains directly through the foundation into the subsoil. It is a proven solution for outdoor courts and has an average lifespan of 25 to 40 years. ZOAB asphalt (open asphalt concrete) works on a similar principle and is in certain situations a good choice.
Supersub works differently: this is a light, self-levelling foam concrete that provides a flat and stable base. The material is shock-absorbing, water-permeable for outdoor courts and in many cases can be poured within a single day. For renovations, such as converting a tennis court into a padel court, the thickness is generally approximately 10 cm. For new builds it is approximately 15 cm.
All foundation components used in the Netherlands must be inspected by Kiwa ISA Sport. This quality mark protects you as the client against materials that do not meet the applicable sports-technical standards. If you work with a provider who is not aware of this, you run the risk that your foundation later fails the certification inspection.
Why does an outdoor court take longer than an indoor court?
An outdoor padel court has a longer lead time than an indoor court, because more phases are involved: a heavier steel structure for wind load, a more complex foundation that depends on the site, and in almost all cases a permit procedure. The combination of these factors makes the preparation more time-intensive.
For outdoor courts, the steel structure must be calculated for the wind zone of the site. The Netherlands has three wind zones, and the structure is adapted for each site to the corresponding load. This requires a structural calculation that takes more time than for a standard indoor court.
For outdoor courts, the foundation is the biggest cost factor and the most time-determining step. The soil conditions, accessibility and civil works required vary widely per site. Cone penetration tests of the soil are always needed in order to give responsible foundation advice. That investigation takes time, but cannot be skipped.
Finally: an outdoor court almost always requires an environmental permit, also because of the effect of lighting and noise on the surroundings. Noise is a serious point of attention with padel. The average sound power level is approximately 10 dB higher than for tennis. An acoustic study is almost always mandatory for sites near homes. Allow 8 to 12 weeks for the permit procedure.
How quickly can a padel court be delivered if the structure is produced in-house?
When the steel structure is produced in-house, the dependence on foreign production schedules and international transport falls away. This shortens the lead time considerably and makes the planning more reliable. In practice this means that the structure is available sooner and that customisation does not cost extra weeks.
Most padel courts sold in the Netherlands are produced in Spain. That import process involves transport time, customs scheduling and dependence on the production schedule of a foreign manufacturer. If there is a delay in production or transport, the entire handover shifts.
With in-house production you have direct control over when a structure is ready. That also makes it easier to respond to a tight schedule, for example when a hall is available on a fixed date, or when a permit has just been granted and you want to start quickly.
We produce the steel structure entirely in our own factory. That gives us the freedom to align the schedule with your project, without depending on a third party abroad. The result: shorter waiting times, more certainty about the handover date and the ability to deliver structural customisation without extra delay.
What are common mistakes that delay the handover of a padel court?
The most common causes of delay when building a padel court are: starting the permit application too late, insufficient soil investigation in advance, lack of clarity about the division of responsibilities between parties, and choosing a provider without full execution capacity. Each of these mistakes can be avoided with good preparation.
Starting the permit application too late
The permit procedure takes 8 to 12 weeks on average. Anyone who waits until the rest of the planning is settled loses valuable time. Start the permit application as early as possible, ideally in parallel with the design phase.
Not having a soil investigation carried out
Without a cone penetration test of the soil, you do not know what is needed for the foundation. Surprises in the subsoil, such as poor bearing capacity, high groundwater or the presence of cables and pipes, can delay execution by weeks. A site check in advance is not a luxury, but a practical necessity.
Working with multiple separate parties
Anyone who buys the groundwork, the structure, the artificial turf and the lighting from different parties runs the risk that the schedules do not line up. If one party is delayed, everything shifts. A complete package from a single source prevents this: there is one point of contact and one responsibility for the handover.
Including noise solutions too late in the design
When sound-absorbing panels are added afterwards to an existing structure, the cage structure in many cases has to be reinforced. Panels reduce wind permeability, so the structure absorbs more wind load. If this was not included in the calculation in advance, adapting the structure costs extra time and money. So always include noise solutions in the design phase.
Would you like to know how long building a padel court takes for your specific site? At I-Padel, we are happy to look at the situation together with you: from soil conditions and permit requirements to production planning and handover date. Take a look at our approach to building padel courts or get in touch directly. We are happy to think along with you, without obligation.
Frequently asked questions
Can I build a padel court without a contractor, and what are the risks?
Technically it is possible to organise parts of the process yourself, but building a padel court requires specialist knowledge of structural calculations, foundation techniques and certification requirements. Without experience, you run the risk that the court does not pass the Kiwa ISA Sport inspection, which means you cannot officially play or rent it out.
Moreover, with some providers the warranty lapses if the installation was not carried out by their own installation crew. Working with a party that handles the entire process is in practice almost always cheaper and faster than coordinating separate parties yourself.
How far ahead of the desired opening date should I start planning?
For an outdoor court, count back at least 6 months from your desired opening date, so that you have enough room for the permit procedure (8–12 weeks), production and delivery, foundation work and installation. For an indoor court without a permit requirement, 3 months is generally feasible, provided there are no unexpected complications in the foundation or planning.
If you want to open at the start of the padel season (spring), it is best to begin preparations as early as autumn. Popular periods are busier for installation crews and manufacturers, so planning early gives you a better position in the queue.
What happens if the Kiwa ISA Sport inspection is failed?
If the court fails the inspection, it may not be used for official matches and competitions under the KNLTB or NOC*NSF. Depending on what is rejected (foundation, structure or artificial turf), adjustments must be made before a re-inspection can be requested.
This costs extra time and money, and can delay your opening considerably. Prevent this by working exclusively with materials and structures that have already been approved by Kiwa ISA Sport, and by scheduling the inspection well before the planned opening date.
Is it possible to convert an existing tennis court into a padel court, and does it take less time?
Yes, converting a tennis court into a padel court is possible and in some cases can be faster than a new-build project, because the existing foundation can be partly reused. Whether the current subsoil is suitable must always be assessed through a site check and cone penetration test, however; an outdated or damaged foundation may still require complete replacement.
When using Supersub as a renovation solution, a layer of approximately 10 cm is generally applied over the existing substrate. Also bear in mind that the environmental permit may equally apply to an outdoor conversion.
What are the consequences of noise issues if I do not include them in the design phase?
Noise is a serious point of attention with padel: the average sound power level is approximately 10 dB higher than for tennis. If sound-absorbing panels are added afterwards, the cage structure in many cases has to be reinforced because the panels reduce the wind permeability.
This leads to extra costs, longer lead times and in some cases to problems with the environmental permit if the acoustic study was not carried out in good time. Always include noise measures in the design phase; this is cheaper, faster and avoids legal complications with local residents or the municipality.
Can I have several padel courts built at the same time, and does that affect the lead time?
Building several courts at the same time is certainly possible and can be more efficient than realising courts separately, because the installation crew, the foundation work and the logistics can be combined. The total lead time of the project therefore does not need to be proportionally longer; in many cases the extra time is limited to the additional installation and foundation days.
It is important, however, that the site offers enough space for simultaneous work and that the permit application covers all courts. Discuss the phasing early in the design process, so that the production and installation schedule can be aligned accordingly.
What questions should I ask a provider before awarding a contract?
Ask at the very least: whether the steel structure is produced in-house or imported (this directly affects lead time and customisation), whether all materials have been inspected by Kiwa ISA Sport, whether the provider handles the complete process including foundation, installation and inspection, and what the warranty terms are in the event of delays or failed inspections.
Also ask about reference projects comparable to your situation: indoor or outdoor, similar soil conditions, similar number of courts. A transparent provider will answer this without hesitation and actively thinks along about the planning and risks of your specific site.