Building a padel court · 14 May 2026 · 11 min read
How long does it take to build a padel court?
Building a padel court takes 10–12 weeks on average. Discover all the phases, possible delays and tips for a smooth completion.

In this article
- How long does it take on average to build a padel court?
- What phases are there in the construction process of a padel court?
- How much time does the foundation of a padel court take?
- What can delay the construction time of a padel court?
- How quickly can a padel court be delivered after ordering?
- Does the construction time differ between an indoor and an outdoor court?
- When is the best time to have a padel court built?
- Frequently asked questions
How long does it take to build a padel court? That is one of the most frequently asked questions from entrepreneurs, clubs and real estate parties who are seriously considering a padel project. The short answer: the installation itself takes 3 to 4 days, but the total process from the first conversation to completion takes 10 to 12 weeks on average.
In this article we explain per phase what exactly happens, where the time goes and what you can do to keep the process as smooth as possible.
How long does it take on average to build a padel court?
Building a padel court takes 10 to 12 weeks on average, from start to completion. The physical construction on site takes only 3 to 4 days. The rest of the time goes on preparation, production, planning and any permit procedures that have to be completed beforehand.
That ratio surprises many people. You would expect construction to take the most time, but in practice preparation is the longest phase. Think of applying for a padel court permit, carrying out structural calculations, producing the steel structure and scheduling the installation crew. Once everything is ready and the permit is in place, the construction itself goes quickly.
For projects in which several courts are built at once, the lead time can be slightly longer due to the larger scale of production and the logistics on site. Even then, however, the installation per court takes relatively little time.
What phases are there in the construction process of a padel court?
The construction process of a padel court consists of five consecutive phases: the preparation phase (permit, design and calculations), the production phase (steel structure and materials), the groundwork and foundation, the installation of the cage structure and the glass, and finally the finishing with artificial turf and LED lighting.
Each phase has its own lead time and dependencies:
- Preparation: Site survey, structural calculation, permit application and final design. This is the phase that can take the most time, especially if an environmental permit is needed.
- Production: The steel structure is produced to size. Depending on the workload in the production schedule, this usually takes a few weeks.
- Groundwork and foundation: Earthmoving, construction of the foundation (drainage concrete, Supersub or ZOAB asphalt) and curing. Outdoor courts take more time here than indoor courts.
- Installation of cage structure and glass: Erecting the steel structure takes about 2 days. The glass around the court is then installed.
- Finishing: Laying the artificial turf, including sand bed and lines, takes 1 to 2 days. The LED lighting is installed straight afterwards.
All these phases have to fit together. Good project planning prevents you from waiting for materials while the crew is already on site, or the groundwork being carried out before the permit is final.
How much time does the foundation of a padel court take?
Building the foundation usually takes 1 to 2 days for an indoor court. For an outdoor court this can rise to several days, depending on the soil conditions, the chosen foundation type and the scale of the groundwork needed beforehand.
The foundation is a part that many people underestimate, both in time and in complexity. There are three commonly used foundation types, each with its own processing time:
- Drainage concrete: A water-permeable concrete floor that drains rainwater directly through the open structure of the material. Suitable for outdoor courts. After pouring, a curing time is needed before installation can begin.
- Supersub: A foundation solution based on foam concrete. This lightweight, self-levelling material can in many cases be poured within one day. It is shock-absorbing, water-permeable (in the outdoor version) and extremely flat, which contributes to consistent ball bounce.
- ZOAB asphalt: Open asphalt concrete that lets water through. Less common for padel, but a good choice in certain situations.
Which foundation type suits best depends on the soil conditions, the use and the budget. All foundation components must be approved by Kiwa ISA Sport in the Netherlands. Working with certified materials is not a formality, but protects you as a client against materials that later turn out not to meet the standards.
What can delay the construction time of a padel court?
The most common causes of delay are a slow permit procedure, bad weather during the groundwork, unexpected soil conditions and late decisions about the design or execution. Applying for a padel court permit takes 8 to 12 weeks on average, and that is often the biggest bottleneck in the entire process.
Delays can in most cases be foreseen and prevented with good preparation. These are the most common bottlenecks:
- Permit procedure: Outdoor courts almost always need an environmental permit. Municipalities apply a statutory decision period, but in practice it can take longer due to additional questions, objection procedures or missing documents. Start early.
- Missing documents: A permit application requires structural calculations, an acoustic study, a lighting study and a site plan. If one of these documents is missing or incomplete, the procedure is delayed.
- Weather conditions: Groundwork and foundation cannot be carried out in frost, heavy rainfall or extreme heat. Preferably schedule groundwork in spring or early autumn.
- Soil conditions: If cone penetration tests show that the soil is weaker than expected, an adapted foundation solution may be needed. This costs extra time and budget.
- Late design changes: Changes to the layout, the type of court or the noise solutions after production has already started always lead to delay.
How quickly can a padel court be delivered after ordering?
After the final order and completion of the permit procedure, the lead time to completion averages 10 to 12 weeks. In situations where no permit is needed, such as with certain indoor courts in existing halls, this can be shorter.
The speed after ordering depends heavily on two factors: the production planning and the status of the permit. When the permit has already been applied for or is not needed, production of the steel structure can start immediately. Once the structure is ready and the foundation has been built, installation follows quickly.
For projects with several courts or special custom requirements, such as sound-absorbing panels or a non-standard layout, it is wise to order earlier. The structural calculations per location take extra time, but they ensure that the court fits exactly with the conditions at your location.
A practical piece of advice: start the permit process and the design process as early as possible, preferably in parallel with the decision-making. That way you avoid having to wait weeks after the final go-ahead before production can begin.
Does the construction time differ between an indoor and an outdoor court?
Yes, the construction time of an outdoor court is generally longer than that of an indoor court. The difference lies mainly in the foundation, the permit procedure and the complexity of the steel structure. An indoor court in an existing hall can sometimes be completed within 6 to 8 weeks. An outdoor court almost always requires the full process of 10 to 12 weeks or more.
Why does an outdoor court take longer?
With an outdoor court, more factors are at play. The steel structure must be made heavier because of wind load and weather influences. The foundation is more complex and highly dependent on the soil conditions at the location. And an environmental permit is almost always needed, including an acoustic study and a lighting study.
Moreover, building an outdoor court is weather-dependent. Groundwork and foundation work cannot be carried out in frost or extreme rainfall. That makes the planning more sensitive to seasonal influences.
What makes an indoor court faster?
With an indoor court in an existing hall, the foundation is often already there or simpler in design. The steel structure does not need to be dimensioned as heavily because wind and weather play no role. And in some cases no separate building permit is needed, although fire safety rules and usage regulations do apply. This can shorten the lead time considerably.
When is the best time to have a padel court built?
The best time to build a padel court is spring (March to May) or early autumn (August to October). In these periods the weather conditions are most favourable for groundwork and foundation, contractors and installation crews are relatively available and you can complete the court in time for the new season.
For indoor courts the season plays a smaller role, because groundwork and foundation are less weather-dependent. Even so, good planning prevents you from having to wait for availability in the busiest construction periods.
Keep in mind that the permit procedure for an outdoor court takes 8 to 12 weeks on average. If you want to build in spring, you must therefore submit the permit application no later than December or January. So start the preparation early: site check, design, structural calculations and gathering the required documents.
At I-Padel we guide the entire process of building padel courts, from the initial exploration through to completion. We coordinate the permit application, take care of the structural calculations and schedule the construction so that you can start on time. Want to know what is needed for your location and when you can start? Get in touch for an initial exploration, we are happy to think along with you, without obligation.
Frequently asked questions
Do I need a separate permit for every padel court?
Not always, but for outdoor courts an environmental permit is almost always required. For indoor courts in an existing hall it depends on the situation: sometimes a notification is enough or only fire safety rules apply. If you build several courts at one location, you usually only need to submit one permit application for the whole project. Always have this checked in advance by a specialist, because a missing permit can lead to the construction being halted.
What does an acoustic study cost and is it mandatory for my project?
An acoustic study is almost always mandatory for outdoor courts as part of the permit application, especially when the court borders homes or other noise-sensitive uses. The costs usually range between €500 and €1,500, depending on the complexity of the location. The study determines whether additional noise measures are needed, such as sound-absorbing panels or a specific orientation of the court. Include this in your total budget and plan the study early in the process.
Can I speed up construction by starting groundwork before the permit is in place?
This is strongly discouraged. Starting groundwork or foundation before the environmental permit has been definitively granted involves major risks: you may be required to undo the work carried out if the permit is ultimately refused or changed. What you can do in parallel is have cone penetration tests carried out and structural calculations drawn up. That way everything is ready to start immediately once the permit is irrevocable.
How do I maintain a padel court after completion and does this affect its lifespan?
Regular maintenance extends the lifespan of your padel court considerably. For the artificial turf this means periodic brushing to keep the fibres upright and the sand bed evenly distributed. The steel structure and the glass should be inspected annually for damage, rust formation or loose connections. Always work with certified materials approved by Kiwa ISA Sport, because they meet the standards that guarantee long-term performance.
What if my location has an irregular or limited space — is custom work possible?
Yes, custom work is possible and in practice is regularly needed. Not every location offers the ideal dimensions or a flat base. Through tailor-made structural calculations and adapted steel structures, a court can be matched to the specific conditions of your location, such as a sloping site, limited clear height for indoor courts or a non-standard floor plan. Do keep in mind that custom work may extend the production time slightly and affects the budget.
How many courts can I have built at the same time and does the lead time scale with that?
Several courts can be produced and built simultaneously, which is more efficient than realising courts separately. The lead time does not scale linearly: the preparation and permit procedure apply to the whole project, and the installation of several courts can be partly carried out in parallel by a larger crew. The logistics on site do increase, however, and the production planning may take a little more time. For projects with four or more courts it is wise to start the preparation extra early.
What are the most common mistakes when planning a padel court project?
The most common mistake is starting the permit application too late, so that the desired opening date proves unachievable. In addition, many clients underestimate the complexity of the foundation and the influence of the soil conditions on the budget. Another common pitfall is making design changes after production has already started, which always leads to delay and extra costs. Make sure the design, the choice of location and the budget are fully settled before you place the order definitively.