Building a padel court · 7 August 2026 · 11 min read
What structural requirements apply to building a certified padel court?
Structural requirements for a certified padel court: dimensions, foundation, steel, glass and lighting. Find out what is technically involved in a Kiwa ISA Sport inspection.

In this article
- Which standards determine whether a padel court is certified?
- What are the mandatory dimensions and measurements of a padel court?
- What requirements apply to the steel structure of a padel court?
- What foundation requirements apply to a padel court?
- What are the requirements for glass, artificial turf and lighting on a padel court?
- Are there additional structural requirements for padel courts with sound-absorbing panels?
- Who is responsible for complying with the structural requirements during construction?
- How I-Padel helps with building a certified padel court
- Frequently asked questions
Building a certified padel court is subject to structural requirements covering dimensions, steel structure, foundation, materials and lighting. These requirements are laid down in national building regulations and international sports standards, and are tested after completion by a recognised inspection body such as Kiwa ISA Sport. In this article we answer the most common questions about what is technically and structurally involved in building a padel court that meets all applicable standards.
Which standards determine whether a padel court is certified?
A padel court is certified when the structure, materials and installation meet the requirements of the Dutch Bouwbesluit (Building Decree) and the international sports standards of the World Padel Tour and the Federación Internacional de Pádel. After completion, an inspection by Kiwa ISA Sport is mandatory for use in official competitions. Kiwa ISA Sport is the recognised Dutch body for the assessment of sports surfaces and sports facilities.
Certification covers several components at once: the steel structure, the foundation, the artificial turf, the glass and the lighting are each assessed separately. All materials used must have been approved in the Netherlands by Kiwa ISA Sport. Anyone who unknowingly works with non-certified components risks the court not being approved for official use. This is a point that less experienced buyers regularly run into.
In addition to the sports-technical inspection, most outdoor courts also require an environmental permit. The municipality assesses structural calculations, an acoustic study and a lighting study as part of this. A padel court without a permit can be shut down or must be removed.
What are the mandatory dimensions and measurements of a padel court?
The official playing dimensions of a padel court are 20 by 10 metres. For assembly, at least 21 by 11 metres of free space is required. The recommended total space including run-off zones is 21 by 14 metres. The minimum clear height for a covered padel court is 6 metres, and the higher the better for playing quality.
The run-off zones at the short ends are not only a matter of playing comfort. They are also relevant to player safety and are taken into account when the facility is assessed. For indoor padel courts in existing halls, the available height is often a limiting factor. A hall with less than 6 metres of clear height is technically not suitable for professional use.
Deviations from the standard dimensions are possible in some cases, but always require a structural recalculation. A court that is smaller or narrower than the standard does not meet the certification requirements for official competitions.
What requirements apply to the steel structure of a padel court?
The steel structure of a padel court must meet the structural requirements of the Bouwbesluit, including calculations for wind load, stability and load-bearing capacity. The structure is calculated per location on the basis of the wind zone, the surrounding buildings and any extra load from sound-absorbing panels. A standard structure without a site-specific calculation does not meet the applicable standards.
Stricter requirements apply to outdoor courts than to indoor courts. The steel structure must withstand the weather, which means heavier steel is used and the structure is hot-dip galvanised to protect against rust. The connections, posts and columns are dimensioned to the wind load that applies at the specific location.
An important point of attention is that the structural calculations must be submitted with the permit application. Without approved structural calculations, the municipality will not grant an environmental permit. This also applies to indoor courts where structural modifications are made to the building.
What foundation requirements apply to a padel court?
The foundation of a padel court must be stable, level and durable, and must be able to absorb the forces from the steel structure and the wind load. The exact foundation build-up is determined on the basis of cone penetration tests of the soil. Without test data, it is not possible to give responsible foundation advice. All foundation materials must have been approved by Kiwa ISA Sport.
There are three common foundation types for padel courts, each with its own technical properties:
- Drainage concrete is a water-permeable type of concrete in which rainwater is drained directly through the foundation into the ground. It is suitable for outdoor courts and has an average lifespan of 25 to 40 years with correct use.
- Supersub is a foundation solution based on foam concrete. It is light, self-levelling and shock-absorbing, and is used for both new builds and conversion projects. The thickness varies from around 10 cm for renovation to around 15 cm for new builds.
- ZOAB asphalt (porous asphalt) is a porous type of asphalt that lets water through and is a good option in certain situations, particularly at locations with specific ground conditions.
For outdoor courts, the foundation is almost always combined with a ring foundation with steel reinforcement, to properly absorb the forces from the steel structure and the wind load. Foundation costs depend heavily on the location and are a significant cost factor for outdoor courts.
What are the requirements for glass, artificial turf and lighting on a padel court?
The glass on a padel court must meet the safety standards for laminated or toughened glass, matched to the structural load and the intensity of play. The artificial turf must be padel-specific, with the right fibre length, infill and ball-bounce characteristics in line with sports standards. The LED lighting must provide uniform illuminance that meets the standards for sports lighting, without disturbing shadows or glare on the playing area.
For the artificial turf, the sand bed and the lines are part of the overall construction and are also included in the inspection. A court with artificial turf that has not been approved by Kiwa ISA Sport does not meet the certification requirements. The same applies to the glass: non-certified glass panels can lead to rejection at the final inspection.
The LED lighting also plays a role in the permit application. For outdoor courts, a lighting study is mandatory as part of the environmental permit. This study demonstrates that the lighting does not cause nuisance to residents. The results of the lighting study are taken into account in the municipality’s assessment. You can read more about the cost structure of a complete court in our overview of the cost of an indoor padel court.
Are there additional structural requirements for padel courts with sound-absorbing panels?
Yes, when sound-absorbing panels are fitted to the outside of the cage structure, the steel structure must be structurally reinforced. The panels reduce the wind permeability of the cage, which increases the wind load on the structure. This requires a new structural calculation per location, using heavier posts, additional columns or adapted connections.
This is a technical point that is regularly underestimated in practice. A standard steel structure that meets the structural standards without panels does not automatically meet those same standards once panels are fitted. Reinforcement is not optional, but an obligation in the interests of safety and service life.
Sound-absorbing panels can be used on both new and existing courts. In both cases the structure must be recalculated before the panels are fitted. For existing courts, this calls for an inspection of the current structure and an assessment of whether reinforcement is possible without replacing the entire steel structure.
Who is responsible for complying with the structural requirements during construction?
Responsibility for complying with the structural requirements lies primarily with the contractor building the padel court. The contractor is obliged to work with certified materials, approved structural calculations and an installation that meets the applicable standards. The client is responsible for applying for the necessary permits, unless this has been transferred to the contractor by contract.
In practice, this means that as a client you need to know exactly what your contractor is supplying and where the responsibilities lie. If you work with several parties, it quickly becomes unclear who is responsible when a component does not meet the standards. This risk is smaller when a single party handles the entire process, from foundation to handover.
After completion, an inspection by Kiwa ISA Sport is mandatory for use in official competitions. The inspection tests whether the court as a whole meets the applicable sports standards. Any shortcomings must be rectified before the court is taken into use for competitive play.
How I-Padel helps with building a certified padel court
We guide the entire process from design to handover, so that the court meets all applicable structural requirements and is ready for inspection by Kiwa ISA Sport. Because we produce the steel structure entirely ourselves, we can structurally calculate every court to the specific requirements of the location. That also applies to more complex situations, such as courts with sound-absorbing panels or locations with a deviating wind load.
What we arrange for you in concrete terms:
- Structural calculation per location, including wind load and foundation advice based on cone penetration tests.
- Supply and installation of all certified components: steel structure, glass, artificial turf and LED lighting.
- All common foundation types: drainage concrete, Supersub and ZOAB asphalt, matched to ground conditions and use.
- Integration of sound-absorbing panels, including structural recalculation.
- Guidance through the permit process, including coordination of the acoustic and lighting studies.
- One point of contact, one responsibility and a 15-year warranty on the steel structure.
Want to know what is needed at your location to build a certified padel court? Get in touch for an initial exploration and we will think along with you, no obligation.
Frequently asked questions
On average, how long does it take to build a certified padel court, from permit to handover?
The total lead time generally varies between 3 and 6 months, depending on the complexity of the location and the speed of the permit process. The permit application itself — including the acoustic study and the lighting study — can take 6 to 12 weeks. It is wise to start the cone penetration tests and structural calculations early in the process, so that you do not lose time once the permit has been granted.
Can I still have an existing non-certified padel court certified?
In some cases this is possible, but it requires a thorough inspection of all existing components: steel structure, foundation, glass, artificial turf and lighting. Components that have not been approved by Kiwa ISA Sport must be replaced before the court qualifies for inspection. In practice, older courts regularly turn out to have several components that do not meet current standards, which can make the conversion costly. A pre-inspection by a certified party quickly gives insight into what is needed.
What are the most common reasons a padel court is rejected at the Kiwa ISA Sport inspection?
The most common rejections relate to non-certified materials (in particular artificial turf or glass panels), a foundation that is insufficiently level or stable, and a lighting installation that does not meet the standards for uniform illuminance. Missing or incomplete structural calculations also regularly cause problems at the final inspection. Most of these risks are avoided by working beforehand exclusively with Kiwa ISA Sport-approved components and certified contractors.
Do the structural requirements also apply to a padel court that is used only recreationally and not for official competitions?
The Kiwa ISA Sport inspection is mandatory for use in official competitions, but the building regulations and the environmental permit apply regardless of the purpose of use. An outdoor court built without an environmental permit can be shut down by the municipality — even if competitive play never takes place. In addition, certified materials and correct construction offer a considerably longer service life and lower maintenance costs, which is a relevant consideration for recreational use as well.
What does a cone penetration test cost and why is it required before the foundation is determined?
A cone penetration test usually costs between €300 and €800, depending on the number of measuring points and the location. The test maps the load-bearing capacity and composition of the soil, which directly determines the type of foundation and the depth of the foundation piles or slab.
Without test data, it is impossible to give structurally responsible foundation advice that meets the requirements of the Bouwbesluit. In practice, skipping this step leads to risks of subsidence or structural instability in the long term.
As a client, do I have to commission an acoustic study myself, or does the contractor arrange it?
The acoustic study is formally the client’s responsibility as part of the permit application, but in practice it is often coordinated by the contractor or project manager. It is important to make clear agreements about this in the contract beforehand, so that there is no uncertainty about who commissions and pays for which study. When a single party guides the entire process, including the permit process, this risk of miscommunication is greatly reduced.
How often does a certified padel court have to be re-inspected after the initial handover?
After the initial inspection by Kiwa ISA Sport, there is no statutory obligation for re-inspection at fixed intervals for recreational use, but for locations that take part in official competitions, federations may impose additional requirements. It is nonetheless advisable to have the court inspected periodically — in particular the steel structure, the artificial turf and the glass connections — to detect wear or structural deviations at an early stage. A proactive maintenance plan considerably extends the service life of the court and prevents costly repairs.